Laying ceramic tile, Mason works, Drywall works, Ceiling works and Finishing work at Foster Electric Factory Project

Laying ceramic tile, Mason works, Drywall works, Ceiling works and Finishing work at Foster Electric Factory Project involves the Decoration, Finishing works. Responsible for the detail works which are included as follows.

♦ Brick Laying work and Plastering Work
♦ Laying floor tiles and wall tiles
♦ Partition of Drywall at office room
♦ Fabrication and Installation of Ceiling Work
♦ Finishing Sealant works

Client ::
Hasty Power Construction Co., Ltd

Location ::
Thilawa SEZ, Thanlyin Township, Yangon Region.

Period ::
Jul-2015 to Sep-2015